Full report
Reducing Russian Involvement in Western Nuclear Power Markets
Commentary by Matt Bowen & Paul M. Dabbar • May 23, 2022
Current Access Level “I” – ID Only: CUID holders and approved guests only. Building Access: Normal building operating hours with exceptions. Read more about the campus status level system and campus access information. See the latest updates to the community regarding campus planning.
Commentary by Matt Bowen & Paul M. Dabbar • May 23, 2022
This commentary represents the research and views of the author. It does not necessarily represent the views of the Center on Global Energy Policy. The piece may be subject to further revision. Contributions to SIPA for the benefit of CGEP are general use gifts, which gives the Center discretion in how it allocates these funds. More information is available at https://energypolicy.columbia.edu/about/partners. Rare cases of sponsored projects are clearly indicated.
The Russian invasion of Ukraine has led to considerable sanctions being levied against Russia.[1] The nation is a major energy supplier to the world—including of oil, gas, coal, and nuclear fuel and reactors—and its energy sector is one area that has already been targeted. Since the war began, some members of the US Congress have called for banning imports of enriched uranium from Russia as soon as 2022 or as late as 2026.[2] This commentary discusses Russian involvement in the Western[3] nuclear power supply chain, particularly in the United States, as well as policy options to reduce—or end—that involvement.
Russia has exported more reactors in recent decades than any other major supplier. In 2021, there were 439 total nuclear power reactors in operation: 38 of them resided in Russia and 42 of them in operation in other countries were of the Russian VVER type (15 of which were in Ukraine). At the end of 2021, 15 Russian-designed reactors were under construction in other nations.
Even for countries that do not host VVERs—including the United States—Russia is a major supplier of several services involved with the manufacturing of nuclear fuel (illustrated in Figure 1). In brief, to make nuclear fuel, raw uranium must be mined out of the ground and milled into uranium-oxide (U3O8) before being shipped to facilities that convert it into uranium-hexafluoride (UF6), which is suitable for enrichment.
Gas centrifuge plants are the type of enrichment facility in use today, where a single centrifuge will take an input stream of UF6 and produce two output streams: one with a higher percentage of the isotope U-235 than the input stream, and a second with a lower percentage of U-235. Enrichment plants can have thousands of centrifuges, and those centrifuges are connected to one another in different ways depending on the company’s goals. Ultimately, an enrichment plant will produce a stream of uranium that is enriched to the desired level (e.g., U-235 content enriched to between 3 percent and 5 percent for use in nuclear power plants) as well as other streams at lower enrichment levels.
In the final step of nuclear fuel making for US power plants, the enriched UF6 is sent to fuel fabrication facilities where it is converted into UO2 and fabricated into fuel pellets. Those pellets are stacked inside metal fuel rods that are connected to each other as part of a fuel assembly, and power reactor cores have many fuel assemblies inside of them.
Figure 1: Creating nuclear fuel for reactors
Russia is not one of the leading miners of raw uranium, as shown in Table 1, though it has substantial involvement in the uranium mining operations of some other countries that have greater production. There are multiple allied nations, such as Canada and Australia, who could increase their uranium mining production, if necessary, to make up for any shortfall that might result from cutting off Russian uranium.
Table 1: Global production of uranium from mines and identified recoverable resources
The next two steps in the nuclear fuel making process, however, involve a large Russian presence in international markets. As Table 2 shows, Russia accounted for nearly 40 percent of global conversion services in 2020. It also shows that several of the existing Western conversion facilities are operating at low utilization rates, which could be ramped up if there was a need. The ConverDyn conversion facility in the United States, for example, closed in 2017 due in part to challenging market conditions (e.g., decreases in demand from Japan and Germany following the Fukushima accident), but the company announced in 2021 plans to restart operations at the plant in 2023.[4] ConverDyn has also stated that it could potentially reinstate a capacity of 15,000 tons of uranium per year should there be a market signal to do so.[5]
Table 2: Global uranium conversion capacity and utilization in 2020
Similarly, Russia has a large presence in the international enrichment market. As Table 3 shows, Russia had around a 46 percent share of global enrichment capacity in 2018. The Russian enrichment entity Tenex provided 30 percent of enrichment services to European Union utilities in 2019.[6] South Korea’s Korea Hydro & Nuclear Power (KHNP) recently signed a contract with Tenex to supply enrichment services out to 2030, reportedly bringing the total value of Tenex’s contracts with KHNP to $2 billion.[7]
Table 3: Global uranium enrichment capacity in 2018 by operator
The price of enrichment services (described as “separative work units” or “SWUs”) has been depressed for years.[8] The low price has led to existing enrichment facilities resorting to a practice known as “underfeeding”: having less natural uranium shipped to them and devoting a greater amount of their capability toward enriching the material that has been produced with lower enrichment levels. In other words, the lower price for enrichment services in recent years has meant that the market is using less uranium mining and conversion services in order to produce the needed amount of low-enriched uranium (LEU) for Western power reactors.
However, if there is a policy in place to reduce or eliminate Russian involvement in Western nuclear fuel markets, this would almost certainly lead to a realignment in the supply chain. In the near-term, the market would likely shift to mining more natural uranium (from non-Russian sources) and raising the low utilization rate of existing Western conversion facilities to closer to their nameplate capacities. This would lead to more expensive fuel for operating reactors and thus will not happen without clear policy direction. (There are no legal or regulatory rules preventing this, and thus if this were the cheaper approach, the market would have already done it.)
No Russian fuel fabrication facilities are involved in the final step of making fuel for US nuclear power plants, but this is not the case for many of the countries hosting Russian VVERs. There is, however, some Western capability to fabricate fuel for those VVER reactors to supplant Russian involvement, if countries so chose. Westinghouse, for example, has the capability to make fuel for Russian VVER-1000s,[9] and could develop the capability to make fuel for other VVER models.
The high level of Russian enriched uranium in US nuclear fuel has a unique history and factors into how the United States got to where it is today in terms of diminished domestic capabilities. In 1993, the Russian Federation and the United States signed an agreement to eliminate excess highly enriched uranium (HEU) from dismantled Russian nuclear weapons.[10] From 1993 to 2013, downblended Russian HEU provided about half of the enriched uranium used in US power reactors, as part of the “Megatons to Megawatts” program.
Separate from the Megatons to Megawatts program, exports of Russian uranium products into the US fuel market have been limited for decades by what is colloquially referred to as “the Russian suspension agreement.” The original agreement was signed on October 16, 1992, when the US Department of Commerce suspended an anti-dumping duty investigation on uranium from the Russian Federation (hence, “suspension agreement”).[11] The agreement restricted the amount of Russian uranium products that could enter the US market, and it has been amended several times since it was first signed. It had previously been scheduled to expire at the end of 2020, but the amendment signed that year extended the agreement to 2040.
In the most recent amendment, the US Department of Commerce and the Russian state nuclear corporation Rosatom agreed to lower the amount of Russian uranium products allowed for export into the US market, and to limit the percentage of US enrichment demand met by Russia to 15 percent starting in 2028. In other words, even before the war in Ukraine began, the US government had been taking steps to reduce Russian involvement in US nuclear fuel markets, both for strategic and commercial reasons.[12] Some of the limits in the suspension agreement are reproduced in Table 4, though only out to 2030.
Table 4: Partially reproduced suspension agreement with limits on Russian exports
As the Table 4 shows, one US company is specifically mentioned in the agreement: USEC,[13] which is today named Centrus. Centrus (located in Ohio) is the sole company with installed enrichment capacity in the United States that is not foreign owned (Urenco, which operates the only commercial-scale enrichment plant in the United States, is owned by the British, Dutch, and German governments). Part of Centrus’s current business model is purchasing enrichment services from Tenex in Russia and supplying Russian LEU to US customers, nominally through 2028, and a congressional intervention to block out Russia, such as the bills mentioned earlier would do, would terminate those contracts.[14]
Previous to the Ukraine invasion, there was a different potential involvement that Russian enriched uranium might have had with some of the future advanced reactors under development in the United States. In recent decades, a variety of private companies have been founded to pursue commercialization of different advanced reactor designs. Some of these designs use uranium with significantly higher enrichments than light water reactors use: instead of 3–5 percent, the enrichments may be as high as 15–19.75 percent. Currently, the only commercial source of this high-assay low-enriched uranium (HALEU) is Russia.
In 2020, the US Department of Energy (DOE) announced a series of large cost-share awards with some of these private reactor developers.[15] For the biggest demonstrations, DOE would contribute a share of the demonstration costs, as long as private entities more than matched that investment. Given that Russia has been the only commercial source of HALEU, some advanced reactor developers were either planning to obtain—or at least considered obtaining—their first fuel load’s worth of HALEU from Russia. In 2018, the Nuclear Energy Institute reported (based on company inputs) that estimated HALEU needs might potentially ramp up from tens of metric tons per year in the mid-2020s to over a 100 metric tons per year in the late 2020s.[16]
Existing enrichment companies, such as Urenco, Orano, GLE, and Centrus, could make HALEU, but these companies would likely be hesitant to invest too much in building HALEU infrastructure and completing NRC licensing without being confident there will in fact be a profitable market for the product. Industry estimates that establishing a commercial-scale production capability would cost more than $500 million.[17] On the reactor developer side, if a single company were to come to an enrichment company and ask to buy only the amount of HALEU they needed—perhaps at the level of tens of metric tons—the price per kilogram of HALEU would be much higher than if the associated development costs could be spread over a large order. Challenges—real and perceived—with HALEU fuel procurement could in turn deter investment in the deployment of some non-light water reactor designs. This is the “chicken and egg” dilemma that the US government is currently grappling with.[18] Buying the first core loads of HALEU from Russia would have enabled reactor developers to easily meet their stated timelines for when they needed fuel. It would also have allowed the federal government to gauge at some level how the construction and operation of the first non-light water reactor projects were executed before committing potentially large amounts of money toward domestic HALEU production.
If the Russian supply option were off the table, however, the United States would need to turn in earnest to remaining possibilities. Congress directed DOE to establish a HALEU availability program in the Energy Act of 2020. At the end of 2021, DOE had already put out a request for information regarding planning for the establishment of a program to support the availability of HALEU for civilian domestic research, development, demonstration, and commercial use,[19] and subsequently received a variety of responses.[20] Multiple bills in the 117th Congress have been introduced that would further authorize and direct DOE to pursue HALEU production programs.[21] Centrus has been working with DOE since 2019 to demonstrate a capability to produce HALEU and obtained NRC approval for HALEU production in 2021.[22]
In addition to a significant exposure to Russia in the uranium fuel chain, the global nuclear market relies on Russia for equipment and construction efforts. Many reactors in operation and under construction around the world are using Russian reactor technology. Given that most of the exported Russian reactors are of the VVER/pressurized water reactor design, we will focus on that technology for this analysis.
Operators of existing nuclear reactors can have significant supply chain exposure to original equipment manufacturers (“OEMs”) of their reactor type. Reactors have unique components that their OEM designed and built for their specific reactor type, including (focusing on the pressurized water reactor design):
In addition to primary components, in various settings around the globe, many different parts of VVER power plant secondary reactor systems could be from Russian origin, including:
Examples of services and components provided to global nuclear customers listed by Rosatom, the state nuclear power company of Russia and the OEM of the VVER reactors, include: assessing and developing key nuclear infrastructure components, large life extension projects, regular supply of spare parts and equipment, and power capacity expansion uprates.[23] In 2019 (the last year Rosatom published an annual report), Rosatom overseas revenues for nuclear fuel assemblies (excluding the uranium supply chain), reactor components, and services was $1.9 billion.[24]
While there is little data on annual maintenance and capital costs for Russian VVER reactors, public data from US nuclear reactors show that annual capital costs for nuclear power plants are $5.35/megawatt-hour (MWh), and annual maintenance costs are $18.27/MWh,[25] of which about a quarter are for physical supplies that have to be purchased.
The list of VVER reactors operating globally (excluding Russia, Belarus, Iran, and China, since those countries are likely to continue using Russian supplies) are listed in Table 5.
Table 5: Global operating VVER reactors in 2021, excluding those in Russia, Belarus, Iran, and China
Exposure of existing nuclear operators to these OEM replacement components is more acute than for typical energy infrastructure for a couple reasons. First, the design requirements for nuclear systems are significantly more stringent than for typical power systems, given failure events are potentially much more acute. As a result, maintenance and procurement teams at existing operators typically return to the OEM for many critical system efforts, and alternative supply chains for replacement nuclear components don’t tend to be well developed. Additionally, nuclear operators culturally tend to be very conservative on procurement of maintenance and upgraded equipment, and tend to default to purchasing from the plant OEM.
There is little public data on maintenance and capital expenditure purchase costs for operating VVER reactors. However, VVER reactors in general are of similar designs, sizes, and capacity factors to US light water reactors, so using the robust US data available is a reasonable surrogate for VVER operating costs. Assuming an 80 percent capacity factor for operating reactors, US data would suggest purchases of capital supplies required to run the existing global fleet is $4.3 billion annually.
While some of the countries listed in Table 5 are less likely to embargo Russian businesses as a result of the Ukraine war, the countries in Europe such as in Bulgaria, Czech Republic, Finland, Hungary, and Slovakia could face important impacts on their abilities to continue to operate their facilities due to parts and services needed from their VVER OEM. The VVERs in Ukraine are in a uniquely challenging position. Some non-Russian engineering and construction companies have built capabilities to replicate Rosatom VVER components, but replicating OEM designs and manufacturing can be a challenge for nuclear power plants.
In addition, Russia, through Rosatom, has been a major potential provider of new nuclear power plants globally. Many plants around the world have been conducting multiyear design and site preparation efforts for the construction of VVER reactors, and many are already in construction. A work stoppage or abandonment of these projects would provide significant financial and energy supply impacts to those countries.
VVER reactors globally under constructed (excluding those in Russia, Belarus, Iran, and China) are listed in Table 6.
Table 6: Global VVER reactors under construction or in planning in 2021, excluding those in Russia, Belarus, Iran, and China
While some of the above are less likely to halt new Russian designed VVER reactor projects as a result of the Ukraine war, ones in Europe such as Finland, Hungary, Slovakia, and possibly Turkey may reconsider development of those plants. Finland already seems to have decided against building a Russian VVER since the Ukraine invasion.[26] As a result, they might have to consider other reactor vendors or look at non-nuclear technologies to fulfill their power needs. Given that power plant development cycles take many years, this could have significant negative impacts on their energy supply and policies.
Countries considering new reactors can simply choose other vendors if they don’t want to be dependent on Russia for fuel, equipment, and services. The US, France, Republic of Korea, and China are all viable reactor suppliers.
Countries that currently host Russian VVERs have a more complicated set of choices to make. They are likely dependent on Russia not just for fuel but for reactor equipment and services. There are some alternatives at least for replacing Russian fuel. Westinghouse, as mentioned, is able to make fuel assemblies for VVER-1000s, and it is possible the company will be able to manufacture fuel for other VVER designs in the near-term.[27] Westinghouse is also able to supply some services to VVERs.[28]
For all other countries with non-VVER power reactors, Russian-mined uranium is not the challenge in extricating themselves from involvement with Russia in procuring their fuel. As shown in Table 1, Russia only mines approximately 6 percent of the uranium produced each year, and other countries can expand production if necessary. Fuel fabrication is also not the challenge.
Instead, policy options to replace Russia’s large presence in global conversion and enrichment services would be where the United States and its allies would need to focus their attention. The conversion and enrichment capacities in Canada, France, Germany, the Netherlands, the United Kingdom, and the United States are enough to replace at least some of the Russian fuel services involved in fueling Western nuclear power plants with greater uranium mining. More investment in mining, conversion, and enrichment facilities may be necessary to fully extricate Western nuclear fuel chains from Russian involvement. However, adding sufficient new conversion capacity and enrichment capacity will take years to accomplish.
In any case, mining, conversion, and enrichment suppliers in the West will be looking to national governments to provide clear policies before they invest money in new facilities and capabilities. Their worry will be that in a year or two, perhaps less, Russian uranium products will be allowed back into national markets and will undercut them, causing them to lose out on their investments. National laws that impose a date for ceasing supplies from Russia—such as the bills cited earlier—would send a clear signal to private markets in the United States and elsewhere so they can adjust efficiently.
International meetings with Western governments could be held to discuss how best to coordinate a reduction or elimination of Russian involvement in their nuclear fuel supply chains. The natural uranium, conversion, and enrichment markets are internationally linked, and national decisions in one country will have impacts on other programs. It will be important for these governments to communicate to the public that all policy options to remove dependency on Russian supply chains are likely to raise costs for operating plants.
The recently created Civil Nuclear Credit Program, established by the 2021 Bipartisan Infrastructure Law,[29] may be able to assist in limiting these impacts, as could the material in DOE’s American Assured Fuel Supply.[30]
The optimal timing of full extrication—for either all Western nations or the United States alone—is beyond the scope of this paper but would certainly be an issue DOE would need to study immediately if it intends to act. The total impacts of a shutoff of Russian uranium products in 2022 are unknown to the authors; the relevant information may exist outside the public realm, though congressional hearings could uncover some of these details. Given the long lead times for ordering nuclear fuel assemblies, the authors do not believe it likely that such a decision would result in outages due to lack of fuel at US power reactors this year, but it is harder to assess impacts in 2023. Other Western governments may also want to use the same non-Russian mining, conversion, and enrichment facilities as part of a similar strategy to reduce Russian involvement in their power markets, raising the prospect of competition for services. The only US conversion facility is still on standby and will not return to producing 7,000 tons of uranium per year until 2023; increasing that capacity to 15,000 tons per year will take longer.
Given these factors and the unique historical context for large amounts of Russian material in US commercial reactors (i.e., the Megatons to Megawatts program), the authors reason that ramping down Russian supplies would happen more smoothly over a period of years not months. This is more consistent with the types of lead times that reactor owners employ for contracts involving different stages of the nuclear fuel cycle.[31] The US government could simultaneously facilitate meetings with Western governments that have mining, conversion, and enrichment facilities to discuss policy options to hasten a greater capability to supplant Russian conversion and enrichment services. Such efforts to strengthen capability may involve a move away from underfeeding existing Western enrichment capacity using increased uranium mining and greater utilization of conversion services. The US government could also consider supporting the construction of a national security compliant fuel chain, given the lack of one using only US-origin technology, equipment, and materials—a national security concern noted by external reports.[32]
It is possible that a nearer-term or even immediate suspension of Russian imports could produce disruptions to the US market that are acceptably small. If this were the case and would not cause existing plants to shut down or experience extended outages, an earlier cutoff is preferable to a later one to minimize dollars sent to Russia as well as US exposure to Russian supply.
Finally, with regard to HALEU production, a logical next step that DOE could pursue is to issue a request for proposals on how best to establish a HALEU production line and see what the private sector proposes. Reports have suggested a combination of government cost-sharing and off-take agreements could form a viable strategy.[33]
[1] Richard Nephew, “The Sanctions War Is Just Beginning: Targeting Russia Was the Easy Part,” Foreign Affairs, March 31, 2022, https://www.foreignaffairs.com/articles/russian-federation/2022-03-31/sanctions-war-just-beginning.
[2] For example, Senator Barrasso introduced legislation with several cosponsors to ban Russian uranium imports 45 days after enactment: https://www.barrasso.senate.gov/public/index.cfm/2022/3/barrasso-leads-bill-to-ban-russian-uranium-importshttps://www.congress.gov/bill/117th-congress/senate-bill/4064.
[3] For the purposes of this paper, “Western” means North America, Europe, Japan, and South Korea.
[4] “US conversion plant gears up for next 40 years,” World Nuclear News, April 14, 2021, https://www.world-nuclear-news.org/Articles/US-conversion-plant-gears-up-for-next-40-years.
[5] ConverDyn, HALEU Workshop, April 28–29, 2020, https://gain.inl.gov/HALEU_Webinar_Presentations/10-Critchley,ConverDyn,Rev1-28Apr2020.pdf.
[6] Euratom Supply Agency, “Annual Report 2020,” table 6 on page 22, https://euratom-supply.ec.europa.eu/publications/esa-annual-reports_en.
[7] “Russia’s Tenex wins tender for fuel supply to South Korea,” Nuclear Engineering International, January 25, 2020, https://www.neimagazine.com/news/newsrussias-tenex-wins-tender-for-fuel-supply-to-south-korea-7653727.
[8] “Enrichment excess is here to stay,” Nuclear Engineering International, October 13, 2015, https://www.neimagazine.com/features/featureenrichment-excess-is-here-to-stay-4691321/.
[9] Westinghouse, “VVER,” https://www.westinghousenuclear.com/operating-plants/nuclear-fuel/vver.
[10] Lawrence Livermore National Laboratory, “A Transparent Success: ‘Megatons to Megawatts’ Program,” Science & Technology Review, April/May 2013, https://str.llnl.gov/content/pages/april-2013/pdf/4.13.3.pdf
[11] International Trade Administration, “2020 Amendment to the Agreement Suspending the Antidumping Investigation on Uranium From the Russian Federation,” Federal Register, October 9, 2020, https://www.federalregister.gov/documents/2020/10/09/2020-22431/2020-amendment-to-the-agreement-suspending-the-antidumping-investigation-on-uranium-from-the-russian.
[12] US Department of Commerce press release, “U.S. Department of Commerce Finalizes 20-Year Amendment to the Suspension Agreement on Uranium from the Russian Federation,” October 6, 2020, https://2017-2021.commerce.gov/news/press-releases/2020/10/us-department-commerce-finalizes-20-year-amendment-suspension-agreement.html.
[13] USEC was the private entity created from the DOE’s enrichment operation. See: https://www.centrusenergy.com/who-we-are/history/.
[14] Centrus, 2020 Annual Report, https://investors.centrusenergy.com/static-files/77087849-8051-4919-a125-d0a8600bcc98.
[15] For example, DOE announced cost-share awards with TerraPower and X-energy on October 13, 2020, US Department of Energy press release, “U.S. Department of Energy Announces $160 Million in First Awards under Advanced Reactor Demonstration Program,” October 13, 2020, https://www.energy.gov/ne/articles/us-department-energy-announces-160-million-first-awards-under-advanced-reactor.
[16] Nuclear Energy Institute letter to Secretary of Energy Rick Perry, July 5, 2018, https://www.nei.org/CorporateSite/media/filefolder/resources/letters-filings-comments/letter-perry-haleu-20180705.pdf.
[17] Nuclear Energy Institute, “Establishing a High Assay Low Enriched Uranium Infrastructure for Advanced Reactors,” January 2022, https://www.nei.org/resources/reports-briefs/establishing-a-haleu-infrastructure-for-advanced-r.
[18] See comments by the French enrichment company, Orano, in “Certainty of demand key to HALEU supply, says Orano,” World Nuclear News, March 15, 2022, https://www.world-nuclear-news.org/Articles/Certainty-of-demand-key-to-HALEU-supply-Orano.
[19] US Department of Energy, “Request for Information (RFI) Regarding Planning for Establishment of a Program To Support the Availability of High-Assay Low-Enriched Uranium (HALEU) for Civilian Domestic Research, Development, Demonstration, and Commercial Use,“ Federal Register, December 14, 2021, https://www.federalregister.gov/documents/2021/12/14/2021-26984/request-for-information-rfi-regarding-planning-for-establishment-of-a-program-to-support-the.
[20] For example, the Nuclear Energy Institute’s response is here: https://www.nei.org/CorporateSite/media/filefolder/resources/letters-filings-comments/NEI-02-14-22_DOE_HALEU-RFI-Response.pdf.
[21] S.4064 and S.4066 from the 117th Congress would support domestic HALEU production.
[22] “Centrus receives licence for HALEU production,” World Nuclear News, June 15, 2021, https://www.world-nuclear-news.org/Articles/Centrus-receives-licence-for-HALEU-production.
[23] Rosatom, “Performance of State Atomic Energy Corporation Rosatom in 2019,” https://www.report.rosatom.ru/go_eng/go_rosatom_eng_2019/rosatom_eng_2019.pdf?msclkid=a5334dd3cf9f11ec964dc636df2b47ef.
[24] Ibid.
[25] Nuclear Energy Institute, “Nuclear Costs In Context,” November 2021, https://www.nei.org/resources/reports-briefs/nuclear-costs-in-context.
[26] Richard Milne, “Finnish group abandons plans for Russia-backed nuclear power plant,” Financial Times, May 2, 2022, https://www.ft.com/content/5e7730b5-be55-48a5-8f55-f67d6fb80d77.
[27] For example, fuel development for VVER-440 has been underway. See: “Westinghouse fuel assemblies delivered to Rovno NPP,” Nuclear Engineering International, July 22, 2021, https://www.neimagazine.com/news/newswestinghouse-fuel-assemblies-delivered-to-rovno-npp-8919297.
[28] Westinghouse, “Westinghouse and NT-Engineering Sign MoC to Increase Nuclear Reactor Power,” September 22, 2021, https://info.westinghousenuclear.com/news/westinghouse-and-nt-engineering-sign-moc.
[29] US Department of Energy press release, “DOE Establishes $6 Billion Program to Preserve America’s Clean Nuclear Energy Infrastructure,” February 11, 2022, https://www.energy.gov/articles/doe-establishes-6-billion-program-preserve-americas-clean-nuclear-energy-infrastructure.
[30] US Department of Energy, “Notice of Availability: American Assured Fuel Supply,” Federal Register, vol. 76, no. 160, August 18, 2011, https://www.govinfo.gov/content/pkg/FR-2011-08-18/pdf/2011-21067.pdf.
[31] “Public Comments on Behalf of the Ad Hoc Utilities Group,” September 25, 2018, page 17, https://www.regulations.gov/document/BIS-2018-0011-0245: “In addition, on average, nuclear generators allow for lead times of 1.7 years for contracts involving various stages of the fuel cycle.”
[32] Energy Futures Initiative, “The U.S. Nuclear Energy Enterprise: A Key National Security Enabler,” August 2017. https://energyfuturesinitiative.org/wp-content/uploads/sites/2/2022/02/The-U.S.-Nuclear-Energy-Enterprise_A-Key-National-Security-Enabler_Report_August-2017.pdf
[33] Nuclear Innovation Alliance, “Catalyzing a Domestic Commercial Market for High-Assay, Low-Enriched Uranium,” April 2022, https://www.nuclearinnovationalliance.org/catalyzing-domestic-commercial-market-haleu.
Microsoft’s plan to restart Three Mile Island points to the way forward.
Nuclear power is being weighed in energy transition plans around the world, as countries seek to replace fossil fuels with low-carbon alternatives while also meeting growing energy demand and maintaining reliability and affordability.
While the United States (US) has facilities that can and do dispose of most low-level nuclear waste (LLW), it does not yet have a viable disposal pathway for two categories of waste: so-called greater-than-class-c (GTCC) nuclear waste, and nuclear waste with characteristics similar to it, or “GTCC-like.”
Full report